Free Sales Ending Soon - 100% Valid PRINCE2-Practitioner Exam Dumps with 285 Questions
Verified PRINCE2-Practitioner dumps Q&As on your PRINCE2 Certification Exam Questions Certain Success!
Topics of PRINCE2-Practitioner Certified Exam
Analyze the application of PRINCE2 principles in context
recommended roles and responsibilities
project plan, stage plan, exception plan, the team plan
the recommended approach to planning, including the recommended approach to defining and analyzing the products
how the themes may be applied
the recommended risk management procedure
the recommended roles and responsibilities
quality planning, quality control, quality assurance
Apply the PRINCE2 requirements for the business case theme, demonstrating an understanding of:
recommended roles and responsibilities
recommended roles and responsibilities
the recommended project management team structure
tolerances and raising exceptions
recommended roles and responsibilities
communication management approach
product description, project product description, quality management approach, quality register
Apply the PRINCE2 requirements for the organization theme, demonstrating an understanding of:
Apply the PRINCE2 requirements for applying the risk theme, demonstrating an understanding of:
recommended roles and responsibilities
outputs, outcomes, benefits, and dis-benefits
Carry out the initiating a project process activity, demonstrating an understanding of:
risk management approach, risk register
exception report, highlight report, lessons log, work package
Apply the PRINCE2 requirements for applying the plans theme, demonstrating an understanding of:
Apply the PRINCE2 requirements for controlling progress, demonstrating an understanding of:
Apply the PRINCE2 requirements for the quality theme, demonstrating an understanding of:
the recommended roles and responsibilities
checkpoint report, daily log, end project report, end-stage report,
benefits management approach & business case
the recommended associated actions
Difficulty in Writing PRINCE2-Practitioner Certified Exam
ExamPrepAway is having a brand value in the market in terms of providing 100% valid PRINCE2-Practitioner dumps pdf. ExamPrepAway worked closely with the PRINCE2 certified industry experts to get a complete understanding of all the exam questions which a participant needs to focus and accordingly we update our dumps which would be providing 100% confidence to the participant to get through with the PRINCE2 exam. All the PRINCE2 dumps provided by us are not just normal Practice Questions and Answers, these are real exam Questions and Answers that you can expect in your actual exam. PRINCE2-Practitioner practice tests with PRINCE2 online Exam Simulator are updated regularly which helps us to get 100% passing results for the participants. We workdays and night to make your life easier and organize all the topics of PRINCE2 Exams for you so that you do not need to spend your time studying a lot of study materials for your exam and get confused about which one is the best guide for you to clear the exam. ExamPrepAway provide quality assured PRINCE2-Practitioner dumps which would be helping you to nail down your PRINCE2 exam.
We provide PRINCE2 Exam test papers for free; you can download them and practice before you decide to buy actual PRINCE2-Practitioner practice exams. you would be able to get a clear idea about how we maintain the quality of the dumps from the provided practice papers, practice test paper would be having a very limited number of questions so would-be encouraging participants to have faith in us and buy the best-provided dumps. we have a 100% money-back guarantee if you were unable to clear your exam after following our exam dumps, we provide a complete assurance that almost 99.5% of candidates manage to crack their PRINCE2 exams from our provided PRINCE2-Practitioner exam dumps, less than 0.5% of customers unable to clear their exam and that also because of the confusion and referring a lot of different websites. We believe in the customer’s trust; we are here to provide the best study materials so that you should not face any hurdles when you are preparing for the exams.
NEW QUESTION 169
Product based planning focuses on which of the following:
1. Creating product descriptions
2. Identifying activities
3. Creating a Product hierarchy
4. Creating a Product sequence
- A. 1, 3, 4
- B. 1, 2, 4
- C. 2, 3, 4
- D. 1, 2, 3
Answer: D
Explanation:
Explanation/Reference:
NEW QUESTION 170
Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for this question in the Scenario Booklet, answer the following 5 questions.
The Stage Plan for stage 3 has been produced.
The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are being taken of the engineering staff performing their everyday duties and operating machinery. Two weeks ago the professional photographer produced the photo session schedule based on the operational staff schedule. The operational staff schedule is produced weekly and maintained by the Engineering Manager.
None of the £500 change budget has been used to date and this is available for the stage.
Which 2 statements apply to the External dependencies section?
- A. Delete entry 5 because the new company logo is being delivered by a separate project and will be detailed in the plans for that project.
- B. Delete entry 7 because it should be shown in the Product Description for the label design.
- C. Delete entry 6 because the customer details were used in stage 2 to create the customer list.
- D. Move entry 5 to Plan description because the new company logo will be delivered during stage 3.
- E. Move entry 5 to Plan prerequisites because the new company logo will influence the label designs.
Answer: B,C
NEW QUESTION 171
Scenario
Additional Information
Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very well. He injured his leg two years ago which has restricted his visits to the engineering area. As CEO he has an overall perspective of the business strategic requirements and the authority to commit resources as required.
Marketing Director: She has been with the company for three years, following a successful career with a publicity company. She has the ability to represent the needs of the business, particularly as this is a marketing project. She has the authority to commit the annual business marketing budget, from which the project will be funded, as she sees appropriate. She will be responsible for monitoring the expected benefits of the calendar, in particular the improvement of the company's image.
Engineering Manager: He has been responsible for many engineering innovations in the company and is still as keen and energetic as the day he started. VVhilst he will not be part of the project team, his staff will feature in the photos for the promotional calendar.
Central Records: This group of five staff looks after all company records and document control. They now maintain all project files.
Bright Lights: This is the local office supplies company. It supplies all the stationery and office equipment needs of the company and will supply the stationery for this project.
Portraits ltd: This is a professional photographic company with a number of excellent photographers and a history of successful work. This company has been selected to take the photos for the company calendar.
It has yet be decided which of the photographers to use.
Which 2 statements explain why the Sales Manager should be appointed as User Assurance for this project?
- A. He is able to advise on suitable stakeholder engagement of current and prospective customers.
- B. He can provide an evaluation of the potential impact the calendar will have on sales.
- C. He joined the company last year with huge enthusiasm and is keen to increase sales.
- D. He can resolve any conflict in requirements between the Sales department and the Marketing department.
- E. He would like to move into the Marketing department in the future and sees this as an opportunity to work closely with the Marketing Director.
Answer: A,B
NEW QUESTION 172
Which statement applies to the Introduction section?
- A. Delete entry 3 because it is the Project Manager's responsibility to implement the Quality Management Strategy.
- B. Delete entry 2 because this is the Project Manager's responsibility.
- C. Delete entry 1 because the project approach is defined in the Project Brief.
- D. Move entry 3 to the Roles and responsibilities section because this is a quality responsibility.
Answer: D
Explanation:
Explanation/Reference:
NEW QUESTION 173
Scenario
Product Summary
A list of customers will be collated. This will use existing information from the Accounts department about current customers, and existing information from the Marketing department about prospective customers.
Using the tariff of mailing costs available from the Post Office, a production cost forecast will be produced to allow the CEO and the Marketing Director to decide whether to continue with the project. If they decide to continue, they will give the approval to launch the internal label design competition. Competition rules will be required to communicate details of the competition to the staff. The chosen label design will then be selected from the competition entries.
The photos for the calendar must be based on existing photo design ideas available from the Marketing department. The selected photos will be chosen from these. Monthly calendar displays will be created to show the required layout of each page.
Product Breakdown Structure (contains errors)
Extract from Stage Plan for stage 3.
(All entries are true statements but may not be shown under the correct heading or in the correct document).
Using the Project Scenario and the Extract from Stage Plan for stage 3 provided as additional intonation for this question in the Scenario Booklet, answer the following 5 questions.
The Stage Plan for stage 3 has been produced.
The Engineering Manager insists that there are to be no interruptions to operations whilst photographs are being taken of the engineering staff performing their everyday duties and operating machinery. Two weeks ago the professional photographer produced the photo session schedule based on the operational staff schedule. The operational staff schedule is produced weekly and maintained by the Engineering Manager.
None of the £500 change budget has been used to date and this is available for the stage.
Which 2 statements apply to the External dependencies section?
- A. Delete entry 5 because the new company logo is being delivered by a separate project and will be detailed in the plans for that project.
- B. Delete entry 7 because it should be shown in the Product Description for the label design.
- C. Delete entry 6 because the customer details were used in stage 2 to create the customer list.
- D. Move entry 5 to Plan description because the new company logo will be delivered during stage 3.
- E. Move entry 5 to Plan prerequisites because the new company logo will influence the label designs.
Answer: B,C
NEW QUESTION 174
Scenario
Extract from the Project Product Description (with errors)
Which 2 statements apply to the Composition section?
- A. Add 'Calendars distributed to customers'.
- B. Move entry 6 to Derivation because this product already exists.
- C. Amend entry 2 to 'Selected paper'.
- D. Delete entry 7 because these will be produced by the photographer.
- E. Delete entry 3 because this is NOT a major product to be delivered by this project.
Answer: C,E
NEW QUESTION 175
Which 2 statements apply to the Development skills required section?
- A. Move entry 13 to Derivation because this is a source of information for this project.
- B. Move entry 13 to Composition because the appointment of the photographer is within the scope of this
project. - C. Delete entry 14 because this skill is NOT required within this project.
- D. Delete entry 15 because this skill is NOT required within this project.
- E. Add 'Knowledge of Data Protection Act.
Answer: D,E
NEW QUESTION 176
Who would be responsible for maintaining the Configuration Item Records?
- A. Project Assurance
- B. Team Manager
- C. Project Manager
- D. Project Support
Answer: D
Explanation:
Explanation/Reference:
Testlet 1
Project Scenario
Calendar Project (Note: The companies and people within the scenario are fictional.) There has been a reduction in fie number of orders at the MNO Manufacturing Company due in part to the increased marketing activities of its competitors. To help counter this, the company has decided to create a promotional calendar for next year for all its current and prospective customers. The end product of this project will be a prepared calendar pack, ready for printing. The design of the calendar will be similar to one sent out previously, and must reflect the company image as described in the existing corporate branding standards. Another project is currently producing a new company logo when is to be printed on each page of the promotional calendar. The prepared calendar pack will consist of:
Design for each month - correctly showing at public holidays and new company logo
Selected photographs- 12 professionally-produced photographs, showing different members of staff
Selected paper and selected envelope - for printing and mailing the calendar
Chosen label design - a competition to design a label will be held as part of this project
List of customers - names and addresses of customers to whom the calendar will be sent.
The project is currently in initiation and will have two further stages:
Stage 2 will include tie activities to:
Create the customer fast using information from the Accounts and Marketing departments
Confirm compliance with the Data Protection Legislation
Create a design for each month - this will be done by the internal creative team
Select and appoint a professional photographer
Gather photograph design ideas from previous project and agree photographic session schedule
Prepare a production cost forecast
Select paper and envelope.
Stage 3 will include the activities to:
Produce and select tie professionally-taken photographs
Hold the label design competition and choose the label design
Assemble the prepared calendar pack.
A production cost forecast, based on the options and costs for the paper, envelope, printing and marketing of the calendar is to be produced in stage 2. However, the actual production and distribution of the calendars is not within the scope of the project. The product cost forecast will be reviewed by the Project Board to determine whether tie project should continue.
It is now 05 October and the prepared calendar pack must be delivered to the print company by 30 November, to enable printing and distribution of the calendar in time for Christmas. The cost of the activities to develop the specialist products and the cost of the project management activities are estimated to be £20,000. There is a project time tolerance of +1 week /-2 weeks and a project cost tolerance of +
£6,000 / -£6,000. A change budget of £500 has been allocated but there is no risk budget.
NEW QUESTION 177
While preparing the Configuration Management Strategy, the Project Manager considered the options for change control. He decided to recommend a change budget of (GBP)250k, but
was undecided on the Change Authority to recommend.
Which option is an appropriate Change Authority for the Outsourcing project?
- A. Senior User(s) and Project Assurance representatives, within the limits of the recommended change budget.
- B. The Director of Facilities and the Director of Information Technology to approve all changes.
- C. The selected service provider to approve and implement all changes.
Answer: A
NEW QUESTION 178
Additional Information Product Description
Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is signed with the selected service provider.
The service level agreement between MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry standards for providing outsourced services.
MFH has a quality management system which contains a document control procedure for all its documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a
formal approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors)
Introduction
1.This document defines the approach to be taken to achieve the required quality levels during the project.
2.The Project Board will have overall responsibility for the Quality Management Strategy.
3.Project Assurance will provide assurance on the implementation of the Quality Management Strategy.
Quality management procedure - Quality standards
4.The selected service provider will operate to industry standards for providing outsourced services.
5.MFH document standards will be used.
Records
6.A Quality Register will be maintained to record the planned quality events and the actual results from the quality activities.
7.Configuration Item Records will be maintained for each product to describe its status, version and variant.
8.Approval records for products that require them will be stored in the quality database. Roles and responsibilities
9.The DIT will check that the employment contracts for outsourced staff adhere to employment law.
10.
Team Managers will provide details of quality checks that have been carried out.
11.
Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process.
12.
The Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.
Which statement applies to the Quality standards section?
- A. Delete entry 5 because the lack of a change management procedure makes the MFH document standards unsuitable.
- B. Add 'All contracts must conform to current employment laws".
- C. Delete entry 4 because external suppliers are responsible for applying any relevant standards to their work.
- D. Add 'PRINCE2 change control procedures will be used to manage any changes to baselined products'.
Answer: B
NEW QUESTION 179
Which of the following statements is False regarding the Risk Management Strategy?
- A. It documents the approach to risk
- B. It captures and maintains all relevant information on identified threats and opportunities
- C. It documents the risk tolerances
- D. It identifies responsibilities towards risk for the project
Answer: B
NEW QUESTION 180
Which 2 statements correctly define a Business Case risk which should be recorded under the Major risks heading?
- A. Operational costs will increase as a result of the recruitment campaign.
- B. If the calendar quality is poor customers will not use it, creating the reverse effect and reducing orders further.
- C. The prepared calendar pack is to be delivered to the printers by the first week in December.
- D. If any competitors launch a calendar at the same time this will reduce the impact of the MNO calendar and benefits will be reduced.
- E. Staff morale will improve as a result of the promotional calendar.
Answer: B,D
Explanation:
Explanation/Reference:
Business Case Theme
Testlet 2
Scenario
A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure to cut costs, better manage suppliers' performance and reduce the confusion caused by inadequate internal controls, outdated standards and outdated technology. External consultants were employed to conduct a feasibility study to identify options to address the problems, and the likely costs and benefits. The following options were considered:
● Do nothing.
● Re-engineer selected business functions.
● Outsource selected business functions.
The feasibility study concluded that there was a case for outsourcing the MFH Information Technology Division and the Facilities Division (maintenance of buildings and grounds). The recommendations were:
● One service provider should be contracted to provide the services currently provided by the Information Technology Division and the Facilities Division.
● A 10-year service contract should be agreed with the selected service provider.
The feasibility study developed high-level designs of the current organization, processes, systems and operating models, plus an outline Business Case for the required project. The external consultants also made the following recommendations for the management of the project:
● Use PRINCE2.
● Set up the project with 4 management stages:
Stage 1. Standard PRINCE2 initiation activities.
Stage 2. Create detailed designs (future organization, processes, systems and operating models) and the service level agreement between MFH and the future service provider.
Stage 3. Request and evaluate proposals, select service provider and agree contract.
Stage 4. Transfer equipment and staff, transfer responsibility for service provision and run trial period.
Initial estimates indicated that the project would cost E2.5m and take two years to complete.
MFH senior management agreed that there was a case for outsourcing, and accepted the recommendations as a basis for the project. There is an expected saving of E20m over 10 years.
The Outsourcing project has completed the Starting up a Project process and is now in the initiation stage.
Because of the strategic importance of the project, the MFH Chief Executive Officer has taken the role of Executive. A PRINCE2-experienced Project Manager has been appointed from within MFH. Staff within the business functions being outsourced will work with the external consultants who conducted the feasibility study to define the detailed designs.
NEW QUESTION 181
What is the purpose of a Product Status Account?
- A. An audit or review to compare actual status of products
- B. A set of records that describe information about the project
- C. A report covering the status about the state of the projects products within
- D. A log used to record problems or concerns about products
Answer: C
NEW QUESTION 182
During stage 1 the level of performance expected from the service provider was changed.
After this change was agreed which of these products will require updating?
- A. Quality Management Strategy because this is where all of the customer's quality expectations of the project's products should be documented.
- B. Project Brief because this is maintained throughout the project to reflect the customer's quality expectations.
- C. Project Product Description because this contains details of the expected performance of the project's products.
Answer: C
NEW QUESTION 183
Extract from the Project Product Description (with errors)
Which 2 statements apply to the Customer's quality expectations section?
- A. Delete entry 17 because this is beyond the scope of this project.
- B. Delete entry 18 because standards should NOT be shown here.
- C. Delete entry 20 because this is an expected benefit and should be recorded in the Business Case.
- D. Delete entry 19 because this should appear in the Product Description for the calendar and not the Project Product Description.
- E. Delete entry 16 because this should be shown on the Product Description for the photos.
Answer: A,C
NEW QUESTION 184
Project Scenario - Health and Safety Training Project:
ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.
ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e-learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.
The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.
The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered.
ABC Company is planning to deliver pilot courses within five months of starting the project.
The ABC Company standard development model for new courses recommends the following stages:
End of the Project scenario.
Additional Information:
The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.
The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.
The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.
The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.
The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.
The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.
The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.
The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.
The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.
The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.
End of the additional information.
ABC Company produces a corporate business plan which includes the targets for the next 12 months. For the Health and Safety Training Project, a feasibility study was carried out and, as a result, the expected sales were included in this plan. During the 'starting up a project' process, the executive advised the project manager that the corporate business plan provides sufficient justification to initiate the project.
Is this a correct application of the 'continued business justification' principle, and why?
- A. Yes, because the executive is responsible for the project's continued business justification.
- B. No, because the feasibility study provides sufficient business justification for the project.
- C. No, because business justification is not required until the 'initiating a project' process.
- D. Yes, because the business justification needs to be recorded and approved in some form.
Answer: A
NEW QUESTION 185
Who is responsible for committing user resources to the project?
- A. Project Board
- B. Senior User
- C. Senior Supplier
- D. Executive
Answer: B
NEW QUESTION 186
Project Scenario
Calendar Project (Note: The companies and people within the scenario are fictional.) There has been a reduction in fie number of orders at the MNO Manufacturing Company due in part to the increased marketing activities of its competitors. To help counter this, the company has decided to create a promotional calendar for next year for all its current and prospective customers. The end product of this project will be a prepared calendar pack, ready for printing. The design of the calendar will be similar to one sent out previously, and must reflect the company image as described in the existing corporate branding standards. Another project is currently producing a new company logo when is to be printed on each page of the promotional calendar. The prepared calendar pack will consist of:
* Design for each month - correctly showing at public holidays and new company logo
* Selected photographs- 12 professionally-produced photographs, showing different members of staff
* Selected paper and selected envelope - for printing and mailing the calendar
* Chosen label design - a competition to design a label will be held as part of this project
* List of customers - names and addresses of customers to whom the calendar will be sent.
The project is currently in initiation and will have two further stages:
Stage 2 will include tie activities to:
* Create the customer fast using information from the Accounts and Marketing departments
* Confirm compliance with the Data Protection Legislation
* Create a design for each month - this will be done by the internal creative team
* Select and appoint a professional photographer
* Gather photograph design ideas from previous project and agree photographic session schedule
* Prepare a production cost forecast
* Select paper and envelope.
Stage 3 will include the activities to:
* Produce and select tie professionally-taken photographs
* Hold the label design competition and choose the label design
* Assemble the prepared calendar pack.
A production cost forecast, based on the options and costs for the paper, envelope, printing and marketing of the calendar is to be produced in stage 2. However, the actual production and distribution of the calendars is not within the scope of the project. The product cost forecast will be reviewed by the Project Board to determine whether tie project should continue.
It is now 05 October and the prepared calendar pack must be delivered to the print company by 30 November, to enable printing and distribution of the calendar in time for Christmas. The cost of the activities to develop the specialist products and the cost of the project management activities are estimated to be £20,000. There is a project time tolerance of +1 week /-2 weeks and a project cost tolerance of +£6,000 / -£6,000. A change budget of £500 has been allocated but there is no risk budget.
Whilst identifying the mailing costs for the calendars the Project Manager was surprised to find the costs could vary considerably depending on the size of the package and the delivery service used. For the purpose of this project, the Project Manager has selected an appropriate service but feels that a corporate standard for postage would have reduced the time and effort invested. It could reduce the company's overheads by up to £20k per year. How should the Project Manager record this observation within the project?
- A. Record the observation in an Exception Report to the Project Board.
- B. Produce a project mandate, outlining the potential savings to be achieved by the introduction of a corporate standard.
- C. Make a note of the observation in the Daily Log to be transferred to a Benefits Review Plan at the end of the project.
- D. Make an entry in the Lessons Log for future consideration by corporate management.
Answer: D
NEW QUESTION 187
The project is in stage 2. The project manager is reviewing stage status and has collected the checkpoint reports from the team managers. These show that the products are being completed on schedule. However, project support has raised issues that quality reviews have not been completed as agreed. The project manager reports in the highlight report that the stage is progressing well.
Is this appropriate, and why?
- A. No, because the issues raised by project support are a cause for concern and should be reflected in the highlight report.
- B. Yes, because the highlight report is a summary of the information in the checkpoint reports.
- C. Yes, because the highlight report is used to provide the project board with stage and project progress.
- D. No, because the project manager should have recorded the cause of the delay to the quality reviews in the lessons log.
Answer: A
NEW QUESTION 188
While planning the initiation stage, the Project Manager reviewed some threats that had been recorded in the Daily Log.
Which threat should have been assessed for possible risk responses to be included in the Initiation Stage Plan?
- A. MFH has no experience in outsourcing and this may affect understanding of what is required, resulting in inadequate plans and strategies.
- B. The Project Brief is a complex document and may not be approved by the Executive.
- C. There is a shortage of service providers so there is a possibility that no suitable service providers respond to the request for proposals. This would prevent the Outsourcing project from proceeding.
Answer: C
NEW QUESTION 189
......
For more info read reference:
PRINCE2-Practitioner Exam Source
PRINCE2-Practitioner Exam Dumps - 100% Marks In PRINCE2-Practitioner Exam: https://www.examprepaway.com/PRINCE2/braindumps.PRINCE2-Practitioner.ete.file.html
Exam Dumps Use Real PRINCE2 Certification Dumps With 285 Questions: https://drive.google.com/open?id=1vajND_S9hi4U9hGJfx83P_MmbWb3WmJc