
[Jan 29, 2022] C-TS422-1909 PDF Questions and Testing Engine With 91 Questions
Updated Exam Engine for C-TS422-1909 Exam Free Demo & 365 Day Updates
C-TS422-1909 Exam Certification Details:
| Level: | Associate |
| Exam: | 80 questions |
| Cut Score: | 55% |
| Languages: | German, English, French, Chinese |
| Duration: | 180 mins |
| Sample Questions: | SAP C-TS422-1909 Exam Sample Question |
NEW QUESTION 51
What do you use to schedule operations from planned orders so that the production plan can be fulfilled?
- A. Supply Network Planning (SNP)
- B. Capacity Requirements Planning (CRP)
- C. Material Requirements Planning (MRP)
- D. Demand Planning (DP)
Answer: C
NEW QUESTION 52
You want to perform capacity availability checks on your production orders. What must be set for this to occur? Note: There are 2 correct answers to this question.
- A. Checking control must have an overall profile assigned in customizing.
- B. Checking rule and group must be assigned.
- C. Indicator Relevant for finite scheduling must be set.
- D. PRT Availability check must be set.
Answer: A,C
NEW QUESTION 53
Which chart types does the tabular planning table provide in SAP S/4HANA? Note: There are 2 correct answers to this question.
- A. Work center capacities chart
- B. Order (pool) chart
- C. Orders (dispatched) chart
- D. Capacity requirements chart
Answer: A,D
NEW QUESTION 54
Which of the following apply to MRP Live?
There are 2 correct answers to this question.
Response:
- A. The definition of the planning scope is more flexible.
- B. Planned orders need to be converted to purchase requisitions for externally procured materials.
- C. The BAdIs for classical MRP also apply to MRP Live.
- D. The sequence of planning materials is calculated across plants.
Answer: A,D
NEW QUESTION 55
In which customizing activity do you set up automatic routing selection for production orders?
Please choose the correct answer.
Response:
- A. Define order-type-dependent parameter
- B. Define production scheduling profile
- C. Define selection profiles
- D. Define scheduling parameters for production orders
Answer: A
NEW QUESTION 56
You want to reduce planning efforts for B/C materials. Which planning procedure do you recommend?
- A. Forecast planning
- B. Consumption-based planning
- C. Material requirements planning
- D. Manual planning without check
Answer: B
NEW QUESTION 57
A customer is considering switching from order-related settlement to product-related settlement. What are capabilities of cost collectors?
There are 2 correct answers to this question.
Response:
- A. They can be applied to make-to-stock production order.
- B. They can be used for manufacturing with collective orders.
- C. They can be used for repetitive manufacturing.
- D. They can be created automatically during month end process.
Answer: A,C
NEW QUESTION 58
How can you limit the validity of a bill of material (BOM)? Note: There are 2 correct answers to this question.
- A. By material type
- B. By period
- C. By industry
- D. By plant
Answer: B,D
NEW QUESTION 59
What are possible configuration steps when setting up the alert monitor in Advanced Planning? Note: There are 3 correct answers to this question.
- A. Create object selection variant for product-related alerts.
- B. Create object selection variant for transportation lane-related alerts.
- C. Assign the overall profile to the authorization profile.
- D. Create object selection variant for resource-related alerts
- E. Assign the alert profile to the overall profile.
Answer: A,D,E
NEW QUESTION 60
Which of the following is used by the MRP Live planning run in SAP S/4HANA?
Please choose the correct answer.
Response:
- A. Parallel processing across servers
- B. MRP list
- C. Planning horizon
- D. Net change planning
Answer: D
NEW QUESTION 61
On which of the following levels can you influence the availability check for the components of production orders?
There are 2 correct answers to this question.
Response:
- A. Production order type
- B. Material master
- C. Production controller
- D. MRP controller
Answer: B,D
NEW QUESTION 62
What capabilities does SAP S/4HANA embedded analytics provide?
There are 2 correct answers to this question.
Response:
- A. Strategic analysis
- B. Real time decision support
- C. Comparison of current data with historical data to identify trends
- D. Automatic update of story boards
Answer: A,B
NEW QUESTION 63
What are attributes of the SAP S/4HANA Simplification list?
There are 3 correct answers to this question.
Response:
- A. It is only a grouping of related technical simplifications
- B. It was created for better planning and estimation of your way to S/4HANA
- C. It can have a business and a technical impact
- D. It details transaction and solution capabilities at a functional level
- E. It contains references to the relevant training material
Answer: B,C,D
NEW QUESTION 64
What is the purpose of collective orders?
- A. To post any component withdrawals single back flush with order confirmation
- B. To manage production orders for an entire finished product on multiple levels
- C. To combine order management of co-products and by-products with the main product
- D. To post production costs on a cost collector instead of the production order
Answer: B
NEW QUESTION 65
What does it mean for the production planner when MRP works with infinite capacities?
- A. MRP creates capacity requirements only if the work center has sufficient capacity.
- B. MRP assigns capacity requirements automatically after the last scheduled order on a work center.
- C. MRP assigns capacity requirements automatically to work center is with the earliest available capacity.
- D. MRP creates capacity requirements without checking the capacity of a work center.
Answer: D
NEW QUESTION 66
The setup time on the production line to produce a material is extensive. You would like to avoid multiple setups and limit the production of the material based on a planning calendar.
Which type of lot size procedure should you use to accomplish this?
Please choose the correct answer.
Response:
- A. Fixed lot sizing
- B. Periodic lot sizing
- C. Exact lot sizing
- D. Minimum lot sizing
Answer: B
NEW QUESTION 67
Which process order function uses a resource network?
Please choose the correct answer.
Response:
- A. Resource selection
- B. Capacity leveling
- C. Capacity planning
- D. Resource scheduling
Answer: A
NEW QUESTION 68
Your project uses process orders for the production of liquid chemicals. What can you define to ensure that the production flow happens only in physically connected tanks?
- A. Work center hierarchy
- B. Resource network
- C. Operation network
- D. Setup matrix
Answer: A
NEW QUESTION 69
What could be the reason for multiple commitment of individual capacities, where several operations have the same scheduled dates on a resource after capacity planning? Note: There are 2 correct answers to this question.
- A. The work center has several individual capacities.
- B. The Change Planning Direct on indicator is set.
- C. Alternative resources are fully occupied.
- D. The planning strategy is infinite.
Answer: A,D
NEW QUESTION 70
Which actions does the system perform by default when you save a confirmation for a finished product in repetitive manufacturing? Note: There are 3 correct answers to this question.
- A. Material staging for next order in sequence
- B. Posting of goods receipt for the product
- C. Posting of production costs to the production cost collector
- D. Archiving of documents for assembly scrap
- E. Reduction of associated capacity requirements
Answer: B,C,E
NEW QUESTION 71
For which data objects do you have to set up CIF integration models in S/4HANA to use them in advanced planning?
There are 2 correct answers to this question.
Response:
- A. Work center
- B. Material master
- C. Contract
- D. Production plant
Answer: C,D
NEW QUESTION 72
During planning you are facing an overload situation on a resource. Which activities do you consider to create a feasible production plan?
There are 3 correct answers to this question.
Response:
- A. Use multilevel MRP run for the products on the resource
- B. Use DS heuristic "Schedule Sequence"
- C. Use a bucket-oriented capacity check
- D. Use rescheduling with an alternative mode
- E. Use optimization with respect to set-up times
Answer: B,D,E
NEW QUESTION 73
In the Schedule Production app, which settings can you make in the planning strategy? Note: There are 3 correct answers to this question.
- A. Planning mode (bucket/sequence)
- B. Direction (forward/backward)
- C. Fixed pegging (on/off)
- D. Finiteness level (0...1)
- E. Scheduling control (finite/infinite)
Answer: A,B,E
NEW QUESTION 74
......
Exam Passing Guarantee C-TS422-1909 Exam with Accurate Quastions: https://www.examprepaway.com/SAP/braindumps.C-TS422-1909.ete.file.html