
SAP C_TSCM42_67 Exam Dumps [2021] Practice Valid Exam Dumps Question
C_TSCM42_67 Dumps - Grab Out For [NEW-2021] SAP Exam
SAP C_TSCM42_67 Certification Exam Topics:
| Topic Areas | Topic Details, Courses, Books |
|---|---|
| Lean Manufacturing (PP-REM, PP-KAB) 8% - 12% | Outline the highlights of repetitive manufacturing and kanban. |
| Material and Capacity Requirements Planning > 12% | Characterize production-relevant planning functionality. |
| Material Requirements Planning (PP-MRP) > 12% | Explore material requirements planning functions. |
| Master Data (LDM) 8% - 12% | Set up master data for production planning and manufacturing. |
| Production Orders Basics (PP-SFC) 8% - 12% | Apply production order functionality. |
NEW QUESTION 29
Which of the following statements about the planning functions available in SAP ECC is correct?
- A. In demand management (DM) material shortage situations are identified and corresponding receipt elements are created.
- B. Long-term planning (LTP) is a long-term form of forecast planning.
- C. Material requirements planning (MRP) includes automatic capacity leveling.
- D. Master production scheduling (MPS) refers to preferred planning of important materials.
Answer: D
NEW QUESTION 30
Which of the following properties about the planning functions available in SAP ECC applies?
- A. In demand management (DM) material shortage situations are identified and corresponding receipt elements are created.
- B. Material requirements planning (MRP) includes automatic capacity leveling.
- C. Long-term planning (LTP) is a long-term form of forecasting.
- D. Master production scheduling (MPS) refers to preferred planning of important materials.
Answer: D
NEW QUESTION 31
During the processing of production orders planned and actual costs are determined.
On which of the following objects can you collect these costs? (Choose two)
- A. Planned order
- B. Product cost collector
- C. Production order
- D. Work center
Answer: B,C
NEW QUESTION 32
What do you have to consider, when you use the ATP (Available To Promise) checks for material? (Choose two)
- A. ATP checks can be adjusted to also consider future requirements and receipts.
- B. ATP checks can be carried out automatically when releasing a production order.
- C. ATP checks are automatically performed during Material Requirements Planning (MRP) runs.
- D. ATP checks are used to evaluate the free capacity on a certain work center.
- E. ATP checks are mandatory for lead-time scheduling.
Answer: A,B
NEW QUESTION 33
You want to reduce the uncertainty caused by fluctuating requirements for a finished product by using a dynamic safety stock in SAP ECC.
On which specifications is the dynamic safety stock calculation based?
- A. The static safety stock per day and the safety time
- B. The static safety stock and the material forecast
- C. The average daily demand and the desired range of coverage
- D. The average daily demand and the safety time
Answer: C
NEW QUESTION 34
Which of the following statements about the SAP Solution Manager listed is correct?
- A. Solution Manager is an add-on industry solution.
- B. Solution Manager is a stand-alone system that communicates with other systems in a system landscape.
- C. Solution Manager is a satellite system in a system landscape.
- D. Solution Manager is part of the SAP ECC System.
Answer: B
NEW QUESTION 35
Which issue can occur if the lot size-dependent in-house production time in the material master is not updated after changing the routing?
- A. Requirements planning creates an appropriate exception message in basic dates scheduling.
- B. Dependent requirements request the components from the bill of materials at wrong times when using basic dates scheduling.
- C. Subsequent capacity planning is no longer possible due to the obsolete scheduling parameters.
- D. Lead time scheduling cannot take place.
Answer: B
NEW QUESTION 36
Which activity can trigger an automatic availability check for the components of a production order?
- A. Order rescheduling
- B. Goods receipt for a missing part
- C. Material staging
- D. Order release
Answer: D
NEW QUESTION 37
In which of the following objects can you activate backflushing of components if you want to use this functionality during order confirmation? (Choose three.)
- A. Work Center
- B. Material Master (Component)
- C. Production Scheduling Profile
- D. Routing
- E. Material Master (Finished Product)
Answer: A,B,D
NEW QUESTION 38
You select the master data for production orders via production versions.
Which information is contained in a production version?
- A. The control parameters for selecting routings and BOM
- B. The routing and BOM alternatives to be used
- C. The default order type to be used
- D. The explosion dates for the routing and BOM
Answer: B
NEW QUESTION 39
Which of the following activities is necessary for the capacity availability check that can be carried out automatically when a production order is released?
- A. Assign an appropriate availability checking rule to the material master for the product.
- B. Set the finite scheduling indicator and assign a checking rule in the work center for the operation to be checked.
- C. Activate the availability check and assign an overall profile in the production scheduling profile.
- D. Activate the availability check and assign an overall profile in the checking control of the order type / plant combination.
Answer: D
NEW QUESTION 40
Which of the following requirements is supported by using process orders?
- A. Linkage of documents to orders
- B. Use of production/resource tools
- C. Use of reference operation sets
- D. Documentation of the production using an electronic batch record
Answer: D
NEW QUESTION 41
What are characteristics of repetitive manufacturing? (Choose three)
- A. Continuous material consumption, production flow and output
- B. Production without using production orders and without status management
- C. Period-based planning of the quantities to be produced
- D. Automatic line loading based on capacity limits across all production lines
- E. Shop fabrication
Answer: A,B,C
NEW QUESTION 42
Which of the following master data can be used with process orders? (Choose three)
- A. Resources
- B. Production/resource tools
- C. Master recipes
- D. Serial numbers
- E. Production versions
Answer: A,C,E
NEW QUESTION 43
Which of the following elements do you have to prepare for costing of a production order to function without errors? (Choose three.)
- A. Propose a standard text key in work center.
- B. Enter formulas for costing in the work center.
- C. Assign a production scheduling profile to the material master (product).
- D. Use an operation control key with the indicator costing-relevant.
- E. Assign costing variants to order type.
Answer: B,D,E
NEW QUESTION 44
What are the consequences of setting a production order to Technically Complete (TECO)? (Choose three)
- A. Capacity requirements are set to null.
- B. The order and its operations receive the system status Locked (LKD).
- C. Confirmations are no longer possible.
- D. The order is no longer relevant for material requirements planning.
- E. Reservations are no longer relevant for material requirements planning.
Answer: A,D,E
NEW QUESTION 45
Which activities lead to a reduction of the capacity requirements for an operation? (Choose three)
- A. Posting the goods receipt for the production order
- B. Rescheduling the operation
- C. Reducing the order quantity
- D. Confirming the operation
- E. Setting the status technically complete (TECO)
Answer: C,D,E
NEW QUESTION 46
Which of the following statements about consumption are correct? (Choose two)
- A. Consumption can take place between order reservations and planned independent requirements, depending on the strategy.
- B. Consumption is restructured with the planning run.
- C. Consumption takes place on the material level between the planned independent requirements and the planned orders.
- D. Consumption parameters (consumption mode and consumption interval) can be set in the material master or in the MRP group.
Answer: A,D
NEW QUESTION 47
Where can you define the default storage location for the material component of a production order? (Choose three)
- A. BOM header (product)
- B. Production version (product)
- C. Production supply area of a work center
- D. Routing
- E. Material master (component)
Answer: B,C,E
NEW QUESTION 48
Where can you define the valid receivers for production order costs?
- A. In the costing variant
- B. In the valuation variant
- C. In the settlement profile
- D. In the production scheduling profile
Answer: C
NEW QUESTION 49
What features related to process orders can be used to fulfill Good Manufacturing Practices (GMP) requirements? (Choose three)
- A. Resource selection
- B. Approved master recipes
- C. Availability check
- D. Electronic batch record
- E. Digital signature
Answer: B,D,E
NEW QUESTION 50
What is a feature of the simu-lation mode for material requirements planning in SAP ECC?
- A. It posts planning results to the database automatically.
- B. It calculates the delay time which may occur in planning.
- C. It triggers multilevel bottom-up scheduling.
- D. It propagates exception messages from a component to the finished product.
Answer: B
NEW QUESTION 51
In which of the following objects can you activate back flushing for production orders? (Choose three)
- A. Work center
- B. Routing
- C. Material master (finished product)
- D. Production scheduling profile
- E. Material master (component)
Answer: A,B,E
NEW QUESTION 52
You want to produce a finished product only when it is requested by a customer order in make-to-order production. However, all assemblies need to be procured beforehand.
How can you fulfill these requirements in SAP ECC? (Choose two)
- A. Use strategy 50 (planning without final assembly) for the finished product and no strategy for all assemblies in the bill of material.
- B. Use strategy 20 (make-to-order production) for the finished product and strategy 70 (planning at the assembly level) for all assemblies in the bill of material.
- C. Use strategy 40 (planning with final assembly) for the finished product and strategy 70 (planning at the assembly level) for all assemblies in the bill of material.
- D. Use strategy 30 (production by lots) for the finished product and strategy 70 (planning at the assembly level) for all assemblies in the bill of material.
Answer: A,B
NEW QUESTION 53
......
C_TSCM42_67 Exam Dumps PDF Guaranteed Success with Accurate & Updated Questions: https://www.examprepaway.com/SAP/braindumps.C_TSCM42_67.ete.file.html